Teacher answer key
Practice papers, grades 4 to 6: answers
36 questions, 32 of them marked (99 marks in all). Question numbers match the page. Use your browser's Print for a copy.
| No. | Question | Answer | Marks |
|---|---|---|---|
| 1 | Non-calculator Grade 4 Write 0.35 as a fraction in its simplest form. Type your answer like 3/8. Uses: Place value Uses: Fractions | 7/20
Working: 0.35 = 35/100. Divide the numerator and denominator by 5: 35 ÷ 5 = 7 and 100 ÷ 5 = 20. Answer: 7/20. | 2 |
| 2 | Non-calculator Grade 4 Work out 2 1/3 + 1 3/4. Give your answer as an improper fraction, like 11/6. Uses: Fractions | 49/12
Working: 2 1/3 = 7/3 and 1 3/4 = 7/4. The common denominator is 12: 7/3 = 28/12 and 7/4 = 21/12. 28/12 + 21/12 = 49/12. Answer: 49/12. | 3 |
| 3 | Calculator Grade 5 In a sale, a set of spanners is reduced by 30%. The sale price is £84. Show that the original price was £120. Uses: Percentages | Written answer: see the mark scheme
Working: The price is reduced by 30%, so the sale price is 100% − 30% = 70% of the original. 70% = £84, so 1% = 84 ÷ 70 = £1.20, and 100% = £120. Check: 30% of £120 = £36 and £120 − £36 = £84, so the original price was £120, as required. | 3 |
| 4 | Non-calculator Grade 5 By rounding each number to 1 significant figure, work out an estimate for (4.87 × 21.2)/0.52. You must show your working. Uses: Place value Uses: Four operations | 200
Working: 4.87 ≈ 5, 21.2 ≈ 20 and 0.52 ≈ 0.5. (5 × 20)/0.5 = 100 ÷ 0.5 = 200. The estimate is 200. | 3 |
| 5 | Calculator Grade 6 A carpenter puts £2500 into a savings account. The account pays compound interest of 4% a year. How much is in the account after 3 years? Type your answer in pounds, like 1234.56. Uses: Percentage change | 2812.16
Working: The multiplier for a 4% increase is 1.04. After 3 years: 2500 × 1.04³ = 2500 × 1.124864 = 2812.16. The account holds £2812.16. | 3 |
| 6 | Non-calculator Grade 4 A plumber and her apprentice share £360 in the ratio 5 : 4. Work out how much the apprentice gets. Type the number of pounds. Uses: Ratio | 160
Working: 5 + 4 = 9 parts, so one part = 360 ÷ 9 = £40. The apprentice has 4 parts: 4 × 40 = £160. Check: the plumber gets 5 × 40 = £200, and 200 + 160 = 360. | 3 |
| 7 | Calculator Grade 4 A shop sells paint in two tins. A 2.5 litre tin costs £14.50. A 4 litre tin costs £22.00. Which tin is the better value for money? You must show your working. Uses: Ratio Uses: Four operations | Written answer: see the mark scheme
Working: 2.5 litre tin: 14.50 ÷ 2.5 = £5.80 per litre. 4 litre tin: 22.00 ÷ 4 = £5.50 per litre. The 4 litre tin costs less per litre (£5.50 is less than £5.80), so it is the better value. | 3 |
| 8 | Calculator Grade 5 A recipe for 15 pancakes uses 240 g of flour. Work out how much flour is needed for 25 pancakes. Type the number of grams. Uses: Ratio | 400
Working: 240 ÷ 15 = 16 g of flour for 1 pancake. 16 × 25 = 400 g. Answer: 400 g. | 3 |
| 9 | Calculator Grade 5 A builder mixes cement, sand and gravel in the ratio 1 : 2 : 5 by mass. He makes 2400 kg of the mix. Cement costs £0.22 per kg, sand costs £0.04 per kg and gravel costs £0.03 per kg. Work out the total cost of the cement, sand and gravel. Type the number of pounds. Uses: Ratio | 135
Working: 1 + 2 + 5 = 8 parts, so one part = 2400 ÷ 8 = 300 kg. Cement 300 kg, sand 600 kg, gravel 1500 kg. Cost = 300 × 0.22 + 600 × 0.04 + 1500 × 0.03 = 66 + 24 + 45 = £135. | 4 |
| 10 | Calculator Grade 6 A paint store has red tins and blue tins in the ratio 3 : 7. There are 12 more blue tins than red tins. Work out the total number of tins in the store. Uses: Ratio | 30
Working: The difference is 7 − 3 = 4 parts, and 4 parts = 12 tins, so one part = 3 tins. There are 3 + 7 = 10 parts altogether: 10 × 3 = 30 tins. Check: red is 9, blue is 21, and 21 − 9 = 12. | 3 |
| 11 | Non-calculator Grade 4 Work out the value of 5x² − 3x when x = −2. Uses: Algebra basics Uses: Negative numbers | 26
Working: 5 × (−2)² − 3 × (−2) = 5 × 4 + 6 = 20 + 6 = 26. Answer: 26. | 2 |
| 12 | Non-calculator Grade 4 Solve 5(x − 2) = 3x + 8. Uses: Solving equations Uses: Algebra basics | 9
Working: 5x − 10 = 3x + 8 2x − 10 = 8 2x = 18, so x = 9. Check: 5 × (9 − 2) = 35 and 3 × 9 + 8 = 35. | 3 |
| 13 | Non-calculator Grade 5 Here are the first four terms of a sequence: 5, 9, 13, 17. Show that 101 is a term in this sequence. Uses: Sequences | Written answer: see the mark scheme
Working: The terms go up by 4 each time, so the nth term is 4n + a number. When n = 1, 4n = 4, so we add 1: the nth term is 4n + 1. Set 4n + 1 = 101. Then 4n = 100 and n = 25. 25 is a whole number, so 101 is a term in the sequence. It is the 25th term. | 3 |
| 14 | Calculator Grade 5 A plumber charges a call-out fee of £40 plus £36 for each hour of work. A job costs £220. For how many hours did the plumber work? Uses: Solving equations | 5
Working: Let h be the number of hours. Then 40 + 36h = 220. 36h = 220 − 40 = 180. h = 180 ÷ 36 = 5 hours. | 3 |
| 15 | Calculator Grade 6 A rectangular worktop has length (x + 5) cm and width (x − 1) cm. Its perimeter is 40 cm. Work out the area of the worktop. Type the number of square centimetres. Uses: Solving equations Uses: Area and perimeter | 91
Working: Perimeter = 2(x + 5) + 2(x − 1) = 4x + 8. 4x + 8 = 40, so 4x = 32 and x = 8. Length = 8 + 5 = 13 cm and width = 8 − 1 = 7 cm. Area = 13 × 7 = 91 cm². | 4 |
| 16 | Non-calculator Grade 4 Triangle ABC is isosceles with AB = AC. Angle A = 48°. Work out the size of angle B. You must show your working. Type the number of degrees. Uses: Shapes and angles | 66
Working: The angles in a triangle add up to 180°. Angle B + angle C = 180 − 48 = 132°. The triangle is isosceles with AB = AC, so angle B = angle C = 132 ÷ 2 = 66°. | 3 |
| 17 | Calculator Grade 5 A 6.5 m ladder leans against a vertical wall. The top of the ladder is 6 m above the ground. Show that the foot of the ladder is 2.5 m from the wall. Uses: Pythagoras | Written answer: see the mark scheme
Working: The ladder is the longest side (the hypotenuse), so the distance d, in metres, from the wall satisfies d² + 6² = 6.5². d² = 42.25 − 36 = 6.25. d = √6.25 = 2.5 m, as required. | 3 |
| 18 | Calculator Grade 4 A circular pond has a diameter of 4.2 m. A gardener wants to put an edging strip all the way round the pond. Work out the length of edging needed. Give your answer in metres, correct to 1 decimal place. Uses: Circles | 13.2
Working: Circumference = π × diameter = π × 4.2 = 13.194… ≈ 13.2 m (to 1 decimal place). The edging needed is 13.2 m. | 2 |
| 19 | Calculator Grade 6 A water trough is a prism. Its cross-section is a triangle with base 40 cm and height 30 cm. The trough is 150 cm long. Work out how many litres of water it holds when it is full. 1000 cm³ is 1 litre. Type the number of litres. Uses: Area and perimeter | 90
Working: Area of the triangle = ½ × 40 × 30 = 600 cm². Volume = 600 × 150 = 90 000 cm³. In litres: 90 000 ÷ 1000 = 90 litres. | 4 |
| 20 | Non-calculator Grade 5 An L-shaped room is made from a rectangle 8 m long and 5 m wide, with a square corner measuring 3 m by 3 m cut out of it. Show that the floor area of the room is 31 m². Uses: Area and perimeter | Written answer: see the mark scheme
Working: Whole rectangle: 8 × 5 = 40 m². Corner removed: 3 × 3 = 9 m². Floor area = 40 − 9 = 31 m², as required. | 3 |
| 21 | Non-calculator Grade 4 A bag has 4 red counters, 7 blue counters and 9 green counters. One counter is taken from the bag at random. Work out the probability that it is not blue. Give your answer as a decimal, like 0.4. Uses: Probability basics | 0.65
Working: 4 + 7 + 9 = 20 counters. P(blue) = 7/20 = 0.35. P(not blue) = 1 − 0.35 = 0.65. (Check: 13 counters are not blue, and 13/20 = 0.65.) Answer: 0.65. | 2 |
| 22 | Non-calculator Grade 5 The mean of six numbers is 7. Five of the numbers are 4, 9, 6, 10 and 5. Work out the sixth number. Uses: Averages | 8
Working: Total of six numbers = 6 × 7 = 42. The five known numbers: 4 + 9 + 6 + 10 + 5 = 34. Sixth number = 42 − 34 = 8. | 3 |
| 23 | Calculator Grade 5 An electrician checks 20 houses and records how many faults she finds in each. 5 houses had 0 faults, 8 houses had 1 fault, 4 houses had 2 faults and 3 houses had 3 faults. Work out the mean number of faults per house. Uses: Averages | 1.25
Working: Total faults = 0 × 5 + 1 × 8 + 2 × 4 + 3 × 3 = 0 + 8 + 8 + 9 = 25. Number of houses = 5 + 8 + 4 + 3 = 20. Mean = 25 ÷ 20 = 1.25 faults per house. | 3 |
| 24 | Non-calculator Grade 4 A spinner has four colours. The probability of red is 0.25 and the probability of blue is 0.4. The probabilities of green and yellow are the same. Show that the probability of green is 0.175. Uses: Probability basics | Written answer: see the mark scheme
Working: The probabilities add up to 1. Red + blue = 0.25 + 0.4 = 0.65. Green + yellow = 1 − 0.65 = 0.35. They are equal, so green = 0.35 ÷ 2 = 0.175, as required. | 3 |
| 25 | Calculator Grade 5 The bar chart shows how many jobs a plumber did on each day of one week. Work out the mean number of jobs per day. Uses: Averages [Figure: Bar chart of jobs per day] | 5.8
Working: Reading the bars: Monday 6, Tuesday 9, Wednesday 4, Thursday 7, Friday 3. Total = 6 + 9 + 4 + 7 + 3 = 29 jobs. Mean = 29 ÷ 5 = 5.8 jobs per day. | 3 |
| 26 | Calculator Grade 4 An electrician quotes for a job. Parts cost £85. Labour is 4 hours at £45 per hour. VAT at 20% is added to the whole of the quote. Work out the total cost including VAT. Type the number of pounds. Uses: Percentages Uses: Four operations | 318
Working: Labour = 4 × 45 = £180. Before VAT: 180 + 85 = £265. VAT = 20% of 265 = £53, so the total is 265 + 53 = £318. (Or 265 × 1.2 = 318.) | 3 |
| 27 | Non-calculator Grade 4 A tiler is tiling a rectangular floor 5 m long and 4 m wide. Each tile is a square with sides of 50 cm. Show that 80 tiles are needed to cover the floor. Uses: Area and perimeter | Written answer: see the mark scheme
Working: Floor area = 5 × 4 = 20 m². One tile = 0.5 × 0.5 = 0.25 m². Number of tiles = 20 ÷ 0.25 = 80, as required. | 3 |
| 28 | Calculator Grade 6 An electrician wires a new socket circuit. The ring needs 24 m of cable and a spur needs 7.5 m. He buys 10% more cable than he needs, to allow for waste. The cable costs £1.85 per metre before VAT. VAT at 20% is then added. Work out the total cost of the cable including VAT. Give your answer in pounds to the nearest penny, like 12.50. Uses: Percentages Uses: Four operations | 76.92
Working: Length needed = 24 + 7.5 = 31.5 m. With 10% extra: 31.5 × 1.1 = 34.65 m. Cost before VAT = 34.65 × 1.85 = £64.1025. With VAT: 64.1025 × 1.2 = 76.923 ≈ £76.92. | 5 |
| 29 | Non-calculator Grade 5 A plumber needs 7 pieces of copper pipe, each 85 cm long. The pipe is sold in 3 m lengths, and each 3 m length costs £8.40. Offcuts that are too short cannot be used. Work out the least cost of the pipe. Give your answer in pounds, like 12.50. Uses: Four operations Uses: Factors and multiples | 25.20
Working: 300 ÷ 85 = 3.5…, so only 3 whole pieces come out of each 3 m length (3 × 85 = 255 cm, leaving 45 cm, which is too short). 7 ÷ 3 = 2.33…, so he needs 3 lengths (2 lengths give only 6 pieces). Cost = 3 × 8.40 = £25.20. | 4 |
| 30 | Calculator Grade 6 A homeowner gets two quotes to retile a bathroom. Quote A is £1250 including VAT. Quote B is £400 plus £38 for each hour of work, and then 20% VAT is added to the total. Quote B says the job will take 22 hours. Which quote is cheaper? You must show your working, and explain your answer. Uses: Percentages Uses: Solving equations | Written answer: see the mark scheme
Working: Labour for B = 22 × 38 = £836. Before VAT: 400 + 836 = £1236. With VAT: 1236 × 1.2 = £1483.20. Quote A is £1250 including VAT. Since £1250 is less than £1483.20, Quote A is cheaper, by £233.20. | 4 |
| 31 | Non-calculator Grade 4 A cut and colour takes 1 hour 45 minutes and starts at 10:20. What time does it finish? Type it in 24-hour time, like 09:15. Uses: Four operations | 12:05 (also accept: 1205, 12.05) Working: 10:20 + 1 hour = 11:20. 11:20 + 40 minutes = 12:00, and 5 more minutes makes 12:05. So it finishes at 12:05. | |
| 32 | Non-calculator Grade 4 A football club sells 240 tickets for an away match. 3/8 of the tickets go to away fans. How many tickets go to away fans? Uses: Fractions | 90 Working: 240 ÷ 8 = 30 for each eighth. 3 × 30 = 90 tickets. | |
| 33 | Non-calculator Grade 5 Three stylists share a £60 tip pool in the ratio 2 : 3 : 1. How many pounds does the stylist with the biggest share get? Uses: Ratio | 30 Working: 2 + 3 + 1 = 6 parts. 60 ÷ 6 = £10 for one part. The biggest share is 3 × 10 = £30. (The others get £20 and £10, and 20 + 30 + 10 = 60 ✓.) | |
| 34 | Calculator Grade 4 A salon charges £28.50 for a cut and blow-dry. A group booking of 3 people gets 10% off the total. How much does the group pay? Type it like 12.50. Uses: Percentages | 76.95
Working: 3 × 28.50 = £85.50. 10% of 85.50 = 8.55. 85.50 − 8.55 = £76.95. | 3 |
| 35 | Calculator Grade 4 Kofi's team scored these goals in 8 matches: 2, 0, 3, 1, 4, 2, 2, 1. Work out the mean number of goals per match. Give your answer to 1 decimal place. Uses: Averages | 1.9 Working: Total goals: 2 + 0 + 3 + 1 + 4 + 2 + 2 + 1 = 15. Mean = 15 ÷ 8 = 1.875, which is 1.9 to 1 decimal place. | |
| 36 | Calculator Grade 5 A stylist is paid £11.40 per hour for the first 35 hours in a week, and time and a half (1.5 times the rate) for every hour after that. Show that she earns £501.60 in a week when she works 41 hours. You must show your working. Uses: Percentages Uses: Four operations | Written answer: see the mark scheme
Working: Normal pay: 35 × 11.40 = £399. Overtime rate: 11.40 × 1.5 = £17.10 per hour. Overtime hours: 41 − 35 = 6, so 6 × 17.10 = £102.60. Total: 399 + 102.60 = £501.60, as the question says. | 3 |